RECONSTRUCTION/EXTENSION OF SZCZECIŃSKA ST. WITHIN THE SECTION FROM ALEKSANDROWSKA ST. TO THE AREA OF PANCERNIAKÓW ST.

Investor/Contracting authority: Łódź – Road Transport Management

Date of development: May 2015 – now

Project description: The subject of the contract is the development of design documentation concerning the reconstruction of Szczecińska Street at a length of about 3 200 m to communicate the S 14 road to the city centre. The project includes a complete set of studies along with obtaining all necessary documents, decisions and arrangements to execute the works, including ZRID decision (Building Permit Documentation (BPD) decision).

Industries/scope:

– GP/G-class roads

– culverts

– temporary traffic organization

– target traffic organization

– environmental protection equipment

– Environmental Impact Report with obtaining an environmental permit (DUŚ)

– water supply network

– rainwater sewage system

– electricity network

– telecommunications network

– green areas design

– STWiORB (Technical Specifications for Execution and Acceptance and Handing-off of The Construction Works)

– bills of quantities and budget estimates